ANARSE’s July site update reports progress at the planned 13.4 MW Caracol solar plant and the Génipailler mini-grid in Milot. At Caracol, most planned panels were reported installed.

At Génipailler, equipment had arrived for a 436 kW solar installation with 900 kWh of storage, and distribution works had begun. The update describes construction, not confirmed commercial operation.

What this means for businesses

Generation equipment is only part of delivery. Distribution infrastructure and commissioning also determine when a business can depend on the electricity supply.